Building Updates
MARCH 2012 UPDATES
4th Floor:
Offices are completed and final punch list is being worked on. We still have conference rooms and research labs to finalize. Targeted date for completion is April 2012.
2ND AND 3RD FLOOR renovations are completed.
1st Floor:
PPH Biometric Clinic/Staging Area and New Patient Waiting Room to be completed by May 2012.
SUTHERLAND Conference Room will re-open by mid April 2012.
New SON Skills Lab to begin construction mid March and scheduled for completion by May 2012.
There are other common areas that we are working on finishing up and will keep you posted on their status! We are on the “home” stretch and looking good!